PPAC Strahlzeitplan

PHELIX beam time plan 2024 (week view)

Week Month Exp. No or Activities Principal Investigator (PI) Link Scientist Area Shifts
01
Jan P218 prep H. Nazary D. Schumacher Z6 -
02
Jan P218 H. Nazary D. Schumacher Z6 10
03
Jan P-21-00003 H. Nazary D. Schumacher Z6 8
04
Jan P-21-00003 H. Nazary D. Schumacher Z6 10
05
Jan Maintenance
06
Feb Experiment
07
Feb P-22-00089 preparation G. Gregori D. Schumacher Z6 -
08
Feb P-22-00089 preparation G. Gregori D. Schumacher Z6 -
09
Feb Maintenance
10
Mar P-21-00008 preparation J. Hornung C. Brabetz PTA -
11
Mar P-21-00008 J. Hornung C. Brabetz PTA 10
12
Mar P-21-00008 J. Hornung C. Brabetz PTA 10
13
Mar Maintenance
14
April Experiment
15
April Experiment
16
April P-22-00135 preparation K. Rezac C. Brabetz PTA -
16
April P-22-00135 K. Rezac C. Brabetz PTA 2
17
April P-22-00135 K. Rezac C. Brabetz PTA 10
18
April P-22-00135 K. Rezac C. Brabetz PTA 8
19
May P-22-00089 preparation G. Gregori D. Schumacher Z6 -
20
May P-22-00089 G. Gregori D. Schumacher Z6 0
21
May
22
May
23
June P-22-00137 preparation Z. Major B. Zielbauer HHT -
24
June P-22-00137 Z. Major B. Zielbauer HHT 12
25
June P-22-00137 Z. Major B. Zielbauer HHT 12
26
June P-22-00137 Z. Major B. Zielbauer HHT 8
27
July Maintenance
28
July P-21-00006 preparation M. Roth J. Hornung HHT -
29
July P-21-00006 M. Roth J. Hornung HHT 10
30
July P-21-00006 M. Roth J. Hornung HHT 10
31
July
32
Aug
33
Aug
34
Aug
35
Aug
36
Sept
37
Sept
38
Sept
39
Sept
40
Sept
41
Oct
42
Oct
43
Oct
44
Oct
45
Nov
46
Nov
47
Nov
48
Nov
49
Dec
50
Dec
51
Dec
52
Dec
total 120

Remarks

  • school holidays are marked in green
  • Abbreviations: Z6 = Z6 Target station at UNILAC, PTA = PHELIX Petawatt target area

Loading...