Week Month Exp. No or Activities Principal Investigator (PI) Link Scientist Area Shifts
01
Jan P218 prep H. Nazary D. Schumacher Z6 -
02
Jan P218 H. Nazary D. Schumacher Z6 10
03
Jan P-21-00003 H. Nazary D. Schumacher Z6 8
04
Jan P-21-00003 H. Nazary D. Schumacher Z6 10
05
Jan Maintenance
06
Feb Experiment
07
Feb P-22-00089 preparation G. Gregori D. Schumacher Z6 -
08
Feb P-22-00089 preparation G. Gregori D. Schumacher Z6 -
09
Feb Maintenance
10
Mar P-21-00008 preparation J. Hornung C. Brabetz PTA -
11
Mar P-21-00008 J. Hornung C. Brabetz PTA 10
12
Mar P-21-00008 J. Hornung C. Brabetz PTA 10
13
Mar Maintenance
14
April Experiment
15
April Experiment
16
April P-22-00135 preparation K. Rezac C. Brabetz PTA -
16
April P-22-00135 K. Rezac C. Brabetz PTA 2
17
April P-22-00135 K. Rezac C. Brabetz PTA 10
18
April P-22-00135 K. Rezac C. Brabetz PTA 8
19
May P-22-00089 preparation G. Gregori D. Schumacher Z6 -
20
May P-22-00089 G. Gregori D. Schumacher Z6 0
21
May
22
May
23
June P-22-00137 preparation Z. Major B. Zielbauer HHT -
24
June P-22-00137 Z. Major B. Zielbauer HHT 12
25
June P-22-00137 Z. Major B. Zielbauer HHT 12
26
June P-22-00137 Z. Major B. Zielbauer HHT 8
27
July Maintenance
28
July P-21-00006 preparation M. Roth J. Hornung HHT -
29
July P-21-00006 M. Roth J. Hornung HHT 10
30
July I023 V. Bagnoud J. Hornung HHT 10
31
July
32
Aug
33
Aug
34
Aug
35
Aug
36
Sept P-23-00197 preparation S. Le Pape B. Zielbauer PTA -
37
Sept P-23-00197 S. Le Pape B. Zielbauer PTA 10
38
Sept P-23-00197 S. Le Pape B. Zielbauer PTA 10
39
Sept
40
Sept
41
Oct
42
Oct
43
Oct P-23-00193 preparation P. Mahmoodi Tavana C. Brabetz PTA -
44
Oct P-23-00193 P. Mahmoodi Tavana C. Brabetz PTA 10
45
Nov P-23-00193 P. Mahmoodi Tavana C. Brabetz PTA 10
46
Nov
47
Nov
48
Nov
49
Dec P-21-00006 preparation M. Roth J. Hornung HHT -
50
Dec P-21-00006 preparation M. Roth J. Hornung HHT -
50
Dec P-21-00006 M. Roth J. Hornung HHT 2
51
Dec Maintenance
52
Dec
total 162